沼气发电机组在制造、实验和准备运输前的任何期间可以让业主或者业主托付的人员进行查看。在不规划公司技术和技术秘密的前提下,业主可以了解生产进程、计划、实验和检验进程。

The biogas generating unit can be inspected by the owner or the person entrusted by the owner at any time before manufacture, experiment and preparation for transportation. Without planning the company's technical patents and secrets, the owner can understand the production process, plan, experiment and inspection process.

(1)、实验对仪器的要求

(1) Requirements for Instruments in Experiments

QQ截图20171025151828.jpg

实验所用丈量仪表的精确度如下:


The accuracy of the measuring instruments used in the experiment is as follows:

电流表---0.5%   ,电压表-----0.5%, 有功功率表---0.5%,

Amperometer - - 0.5%, voltmeter - - 0.5%, active power meter - - 0.5%.

无功功率表---0.5%,功率因数表---1%,频率表---0.5%

Reactive power meter - - 0.5%, power factor meter - - 1%, frequency meter - - 0.5%.

?实验所用的温度表及压力表精度不低于1级。

The accuracy of the thermometer and pressure gauge used in the experiment is not less than 1 grade.

丈量绝缘电阻使用500V兆欧表。

500V megohm meter is used to measure insulation resistance.

(2)、燃气发电机组的刹车实验

(2) Braking experiment of gas-fired generating units

?根据各种不同工况,将作发电机组的停机实验。

According to different working conditions, the shutdown test of generator set will be done.

?具体内容参照下表内机组实验的内容。

The specific content refers to the contents of the unit experiment in the table below.

(3)﹑机组配套前,其单机燃气发动机按规则进行出厂实验,单机实验完成后与发电机配套成发电机组进行出厂实验。所有这些实验与测试程序均可承受业主的查看,实验完毕后填写完好的实验报告

(3) Before the unit is matched, the single engine gas engine is tested in accordance with the rules. After the single engine experiment is completed, the generator set is matched with the generator to carry out the factory experiment. All these experiments and testing procedures can withstand the owner's inspection, and complete the experiment report after the experiment is completed.